What LOD 350 means
LOD 350 is LOD 300 plus the interfaces. An element is still at its designed size and place, and now everything it needs from its neighbours is modelled as well: the hole it passes through, the hanger it hangs from, the plate it is bolted to, the zone that must stay clear in front of it. Those interfaces can be measured, so the trades can agree on them before anything is made.
BIMForum calls it the level of construction coordination. It usually needs craft knowledge, so it is often modelled by the trades or with them. In one shared model that is where the most expensive mistakes are caught: a duct through a beam, a pipe with no room for its insulation, a door hitting a column.
The interfaces LOD 350 asks for
- Penetrations through walls, floors and beams at their rough opening size
- Supports: hangers, trapezes, clamps, brackets, base plates and the structure they hang from
- Connections between members: base plates, gusset plates, end plates, anchor rods, cap plates
- Joints: expansion, control and movement joints at their place
- Embeds, dowels, sleeves and anchor elements where one trade sets something into another's work
- Access and code clearances: the space to open a panel, service a unit, pass a door
- Insulation on pipes and ducts at its real thickness, and the slope of a drain
Coordinate in Calq, step by step
- Bring the trades together: in one model, or each trade in its own Calq model linked to the others (the Project menu, Any time, Linked models; link_model). Map the storeys of a linked model to yours in one step (take_link_storeys).
- Read the clashes by kind: structure against architecture, services against structure, services against each other, walls and voids (coordination_report, clash_report, check_links).
- Let Calq clear what is safe to clear in one undo step: the services moved clear of the structure and of each other by the coordination priority, the run that can move least staying put (coordinate_model, fix_clashes; across links, coordinate_links).
- Make the openings: each run that passes a wall or a slab gets a real opening at its rough size, made by the owner of that wall; across linked models the other model asks and the owner makes it, both reading the same key for the hole.
- Hang the services: hangers, trapezes and riser clamps laid from where the runs and the structure stand, at the spacing you give (set_supports), and listed with the runs left unhung (support_schedule).
- Connect the steel: base plates, end plates, fin plates, gussets and splices with their plates and bolts on each member end (set_connection).
- Raise what a person must decide as an issue, and send it as BCF to a party not in Calq (raise_issue, export_link_requests).
Check LOD 350 before the trades start
- The coordination report reads clean, or each remaining clash is an issue with an owner
- Every run that crosses a wall or a slab has its opening, and every opening has its run
- Every run is hung, or its exception is said
- The IFC carries the openings, the provisions for voids asked of other parties, and the supports
Moving to LOD 400
With the interfaces agreed, each trade develops its own elements for the workshop: the bars with their shapes, the steel parts with their welds and holes, the services cut into the lengths a shop makes. The next page and the trade pages show how.
Questions
What is the difference between LOD 300 and LOD 350?
LOD 350 adds the interfaces: openings, supports, connections, joints and clearances, modelled so that the trades can measure and agree on them.
Who models LOD 350?
Neither the AIA nor BIMForum says. Often the trades with the design team; in Calq both work on the same model or on linked models, so nothing is redrawn.
Does Calq fix clashes by itself?
It clears the ones that are safe to clear, in one step you can undo, and says what is left for a person to decide.
Can I coordinate with a consultant who does not use Calq?
Yes. The holes your model asks of theirs go out as IFC provisions for voids, and every hole and clash as a BCF topic their tool can open.