Workflows / Scaffolding as temporary works
Scaffolding as temporary works
Scaffolding treated as the temporary works it is: who designs and checks it, loads and platforms, guardrails and fall protection under OSHA 1926 Subpart L, ties to the building, inspection, and how to plan it with the building model.
- Available
- Free account
Why scaffolding is temporary works
A scaffold is a structure: it carries people, materials and wind, and it is tied to a building that may itself be unfinished. It is designed, checked and handed over like one. In the UK, BS 5975 sets the temporary works procedure: a coordinator, a design brief, a design check and a permit before loading. Configurations beyond the supplier's or the industry's standard designs are designed by a competent engineer.
Loads and platforms
- In the United States, OSHA 29 CFR 1926.451(a)(1) requires each scaffold and each component to support its own weight and at least four times the maximum intended load.
- The working platform is chosen for the work, from light inspection to heavy masonry, and its permitted load is marked on the scaffold.
- Platforms are fully boarded between the guardrails, with no gaps people or materials can fall through.
Falls and guardrails
- OSHA 1926.451(g)(1) requires each worker on a scaffold more than 10 feet (3.1 m) above a lower level to be protected from falling to that level.
- Open sides and ends of a platform take a guardrail at the height the rule sets, a midrail about halfway between it and the platform (OSHA 1926.451(g)(4)), and toe boards where objects could fall on people below (1926.451(h)).
- Safe access: stairs or ladders built into the scaffold, never climbing the frame.
Ties and the building
A scaffold is stable only when tied to the building at the spacing its design sets. The ties need anchor points the structure can take, and they move as the facade goes up; planning them with the architect and the facade contractor avoids anchors drilled through finished cladding.
Planning it with the model
A scaffold modelled round the building shows its lifts, ties, access, loading bays and its clash with the crane and the hoarding. Calq lays a tube-and-coupler scaffold round the faces of a building as temporary elements, drawn in every view and checked against OSHA 1926 Subpart L, with every figure it assumed stated for the temporary works designer; no load is checked.
Common mistakes
- Loading a scaffold before it has been handed over and tagged.
- Ties removed by the facade trade and not replaced.
- An inspection scaffold used as a loading platform.
- The scaffold's footprint missing from the site plan and the crane's path.
Questions
How often is a scaffold inspected?
Before first use, after anything that may have affected it, and at the intervals the national rule sets.
Who designs a scaffold?
A competent scaffold designer for anything beyond the standard configurations; the temporary works coordinator checks the design and gives the permit to load.
Is a mobile tower a scaffold?
Yes. It follows its own standard (EN 1004 in Europe) and the maker's instructions.