Workflows / Volumetric modular construction: from design to factory
Volumetric modular construction: from design to factory
How a building is designed as volumetric modules made in a factory: module sizes set by transport and lifting, the structure and services strategy, connections and tolerances, the factory drawings and schedules, and the decisions that must be taken early.
- Available
- Free account
What volumetric construction is
Volumetric modules are three-dimensional units, whole rooms or parts of rooms, made and finished in a factory and set on site by crane. Unlike panel systems, much of the fit-out, services and finishes is done before the module leaves the factory. Design for manufacture and assembly (DfMA) brings the factory's rules into the design from the first sketches.
Decisions to take early
- The module grid: the largest module the roads of the route allow and the crane can lift sets the widths and lengths. These limits differ by country, route and site.
- Where modules meet: structure, fire separation and acoustic separation all double at the joints, with two floors, two ceilings and two walls; the storey height must hold both.
- The services strategy: vertical risers aligned through the stack, horizontal connections made in corridors or in accessible zones at the module joints.
- The ground floor and the core are often cast in place, with the modules stacked above them.
- Irregular and curved plans are cut into modules that repeat, so that the factory makes as few types as possible.
Connections and tolerances
Modules connect to each other and to the foundation with bolted or welded plates at their corners, designed for lifting, transport and the finished structure. Tolerances build up over the storeys, so the connections allow adjustment and the setting out is checked level by level.
From the model to the factory
Calq cuts a building into modules on the same lines at every storey, schedules them in crane order and draws the factory set; an arched wall is cut along its curve where it crosses a module joint.
- A module schedule: each module's type, size, weight, what it holds and where it goes.
- Module drawings: the plan and the four walls of each type, with its openings, connections and services points.
- The lifting points, centre of gravity and the delivery and setting sequence, so modules arrive in the order they are placed.
Common mistakes
- Choosing module sizes after the plan is fixed.
- Forgetting the double floor and ceiling in the storey height.
- Services crossing module joints in places no one can reach once the modules are set.
- No allowance for the crane's reach and the delivery route on a tight site.
Questions
Is modular always faster?
Site time is shorter because the factory works while the foundations are built, but design decisions must be taken earlier, and late changes cost more.
What limits the size of a module?
The transport rules on the route, the crane and the access to the site, which differ by country and by project.
Can a curved building be modular?
Yes, cut into modules that repeat, with the curve taken up in the joints or in the facade.