Volumetric modular construction: from design to factory

How a building is designed as volumetric modules made in a factory: module sizes set by transport and lifting, the structure and services strategy, connections and tolerances, the factory drawings and schedules, and the decisions that must be taken early.

What volumetric construction is

Volumetric modules are three-dimensional units, whole rooms or parts of rooms, made and finished in a factory and set on site by crane. Unlike panel systems, much of the fit-out, services and finishes is done before the module leaves the factory. Design for manufacture and assembly (DfMA) brings the factory's rules into the design from the first sketches.

Decisions to take early

Connections and tolerances

Modules connect to each other and to the foundation with bolted or welded plates at their corners, designed for lifting, transport and the finished structure. Tolerances build up over the storeys, so the connections allow adjustment and the setting out is checked level by level.

From the model to the factory

Calq cuts a building into modules on the same lines at every storey, schedules them in crane order and draws the factory set; an arched wall is cut along its curve where it crosses a module joint.

Common mistakes

Questions

Is modular always faster?

Site time is shorter because the factory works while the foundations are built, but design decisions must be taken earlier, and late changes cost more.

What limits the size of a module?

The transport rules on the route, the crane and the access to the site, which differ by country and by project.

Can a curved building be modular?

Yes, cut into modules that repeat, with the curve taken up in the joints or in the facade.