Service penetrations through the structure: sleeves, critical zones and coordination
How to coordinate ducts, pipes and cables that pass through beams, columns, slabs and walls: where a hole may and may not go, sleeves and provisions for void, fire stopping, who makes the hole, and how a federated model settles each one before the works.
- Available
- Free account
Why penetrations are a coordination problem
Every service crosses the structure somewhere, and each crossing involves three people: the services engineer who needs the route, the structural engineer who must keep the member's strength, and the architect who keeps the fire and acoustic separations. A hole agreed late is either cored on site through the reinforcement, or forces the services into a longer, lower route.
At LOD 350 every penetration is modelled at its rough size, with its sleeve or provision, so that each one is agreed before the shop drawings.
Where a hole must not go
- Near the supports of a beam, where shear is highest and where seismic design codes such as ACI 318 confine the beam over a set length; holes stay out of that zone unless the engineer designs them in.
- At the foot and head of a column, the zones of most confinement, whose length the design code sets from the column's size and clear height.
- Through the compression zone of a beam at mid-span, through a transfer member, or within the punching zone around a column in a flat slab.
- Through a post-tensioned slab where a tendon runs: tendons are located before any core is drilled.
Where a hole can usually go
- Through the web of a beam near mid-span and mid-depth, its size limited by the engineer, with reinforcement round the larger openings.
- Through a slab in the zones the engineer has marked free, with trimmer bars round openings above a set size.
- Through walls, the wall's owner making the opening and restoring its fire and acoustic rating round the service.
Sleeves, provisions and fire stopping
- A sleeve is cast in before the pour, sized for the service plus its insulation and its movement; coring later costs more and may cut bars.
- Where the exact position is not yet final, a provision for void is modelled: a space the structure keeps free, written to IFC as a provision for void so that both disciplines name it the same way.
- Where a service crosses a fire-separating wall or floor, the opening is sealed with a tested fire-stopping system for that service and that element, and a duct takes a fire damper.
Who makes the hole
One simple rule settles most disputes: the owner of the wall or slab makes its holes, and the discipline that owns the run asks for them. In a federated model each request carries one identity in both models, so it can be asked, made, moved or refused while both sides see the same state. Calq keeps this rule across linked models, and writes the requests as IFC provisions for void and BCF topics for a party working in another tool.
Common mistakes
- Holes agreed by email and never modelled, so the next revision covers them over.
- A sleeve sized for the bare pipe, with no room for its insulation.
- Coring through a beam's end zone because the route was fixed before the structure.
- Openings in fire walls with no fire stopping specified.
Questions
What is a provision for void?
A space kept free in the structure for an opening, agreed before the exact service is known. IFC writes it as a building element proxy of type PROVISIONFORVOID, so other tools read it.
When should penetrations be agreed?
Before the structural drawings are issued for construction: at LOD 350, once the services are routed and sized and the structure is fixed.
Can services pass through a column?
Rarely, and only by the engineer's design: a column carries the frame's loads and is confined at both ends. Services normally run beside it.