Workflows / Concrete construction joints: where to place them and how to detail them
Concrete construction joints: where to place them and how to detail them
Construction, movement and isolation joints in cast concrete: what each one is for, where a construction joint belongs in a slab, beam, wall or footing, how it is prepared and reinforced, waterstops below ground, and the mistakes that let in cracks and water.
- Available
- Free account
Three kinds of joint, three jobs
A construction joint is where one pour stops and the next begins. It is not meant to move: the two pours must act as one, so the joint carries shear through the reinforcement that crosses it, its roughened surface and, where needed, a keyway. A movement joint lets the structure expand, shrink or settle without cracking where nobody wants it, and is detailed to open and close. An isolation joint separates elements that must move independently, such as a ground slab from a column or a wall.
Mixing them up is the most common error on drawings: a movement joint drawn with continuous bars cannot move, and a construction joint left without bars across it becomes a crack.
Where a construction joint belongs
- In slabs and beams, where the shear is low, usually towards the third points of a span, and never over a support or under a concentrated load unless the engineer designs it so.
- In walls, horizontally at a floor or a kicker, and vertically at the length the contractor can place and compact in one pour.
- Where the engineer has set it on the pour plan: a joint added on site is agreed with the designer before the pour, never after.
- Away from openings and re-entrant corners, where the section is weakest and shrinkage concentrates.
Preparing and reinforcing the joint
- The face of the first pour is roughened to expose the aggregate and cleaned of laitance before the next pour, so that the two bond. Eurocode 2 (EN 1992-1-1) classes such an interface by its roughness and takes its shear resistance from that class and from the reinforcement crossing it.
- The bars run through the joint, lapped or continuous as the design asks; the stop end is formed so that they pass without being cut.
- Below ground and in water-retaining work, a waterstop crosses the joint: a cast-in PVC or rubber strip, a swelling strip or an injection hose, chosen with the waterproofing designer.
- A keyway, a groove formed in the first pour, adds a mechanical interlock where the shear is high, for example at the base of a wall.
Movement and isolation joints
Movement joints are set by the engineer from the element's length, its restraint, the climate and the shrinkage of the concrete. They break the reinforcement, or carry the load across it on a dowel that slides in a sleeve, are sealed with a sealant over a backer rod, and run through every layer above: a floor finish or a facade laid across a structural joint will crack along it.
Saw-cut contraction joints in a ground slab are cut as soon as the concrete takes the blade without ravelling, to the depth the slab's design sets; cut late, the slab cracks first.
Common mistakes
- Joints shown on the architect's plans but not on the structural drawings, or the other way round.
- A construction joint through a beam at the face of a column, where the shear is greatest.
- No waterstop at the kicker of a basement wall, the first place water finds.
- Screeds, tiles and cladding laid continuously over a movement joint.
Joints as part of the model
When joints are elements of the model rather than lines on a plan, the pour plan, the slab layout, the waterproofing and the finishes all read the same joint. In Calq the construction joints follow the pours of the pour plan with their bars, keyways and waterstops, and go to the IFC with the rest of the structure.
Questions
Is a construction joint a weak point?
Not when it sits where the shear is low, is roughened and cleaned, and is crossed by the designed reinforcement: it then works with the rest of the element. It becomes one when it is placed where the engineer did not plan it, or left smooth.
Can the contractor move a construction joint?
Only with the designer's agreement. A joint changes how shear and shrinkage act, so its position is part of the design.
Do movement joints carry bars?
They are detailed so the element can move: the bars stop at the joint, or a dowel in a sleeve carries load across while letting the element slide.