LOD 100: concept, zones and figures

LOD 100 step by step: what an element is at the concept stage, what it may and may not be used for, and how to set up the project, study the plot and draw massing options in Calq before any wall exists.

What LOD 100 means

At LOD 100 an element exists in the model, but not yet as itself. It may be a symbol, a zone, a mass that stands for a whole building or a figure carried by another element: the floor area of a mass, a cost per square metre, a cooling load per room. Its place is approximate and nothing measured from it is reliable.

That is not a weakness. LOD 100 is where the decisions that cost least to change are made: how much building, where on the plot, in what form, for what brief. A good LOD 100 model answers those questions quickly and honestly, and says which figures are assumed.

What each trade looks like at LOD 100

Build it in Calq, step by step

What LOD 100 may be used for

Moving to LOD 200

Choose the option. In Calq the chosen masses become the contract the next stage works to: the engines lay walls, floors, cores and rooms inside them, and the masses can be kept as a reference or taken out. Nothing is redrawn.

Questions

Can an LOD 100 element be a 3D mass?

Yes. A mass, a zone or a symbol are all LOD 100 when only their existence and approximate extent can be relied on. What makes it LOD 100 is the reliability, not the shape.

Can I get quantities at LOD 100?

Areas, yes: gross floor area by mass and by storey. Quantities of materials, no: there are no materials yet to count.

Does Calq choose the massing for me?

No. Calq draws different options and measures them; the choice is yours. You can ask for others, or move and reshape a mass by hand before the next stage works inside it.