Level of development (LOD) in BIM: the complete guide
What each level of development means for every element of a building, how LOD differs from the level of information need, who models what at each stage, and how to build, check and deliver each level in one Calq model.
- Available
- Free account
What a level of development is
A level of development, LOD, says how far an element of a BIM model can be relied on. It is a promise about one element at one moment: that its size, its shape, its place and the information it carries are developed enough for the job the next person will do with it. It is not a grade of the whole model and it is not a measure of how pretty the 3D looks.
The levels come from the AIA's E201 exhibit (2022) for sharing models between the parties of a project, and are expanded element by element in the BIMForum Level of Development Specification (2025 is the current edition), which also sets each level against the aspects of ISO 7817-1. Each level adds to the one below it: what was true at LOD 300 is still true at LOD 400.
One model holds many levels at once. Early in design the structure can stand at LOD 300 while the services are still LOD 100 zones; on site the steel is LOD 400 for the fabricator while the furniture stays LOD 200. An execution plan says which element must reach which level by which stage, and the model is checked against that table, not against a single number.
The six levels at a glance
- LOD 100: the element exists, as a symbol, a zone or a figure carried by something else (an area, a cost per square metre, a cooling load). Nothing measured from it is reliable.
- LOD 200: a generic 3D placeholder you recognise as what it is (a wall, a beam, a pump), at an approximate size, place and count.
- LOD 300: the element as designed, at its true size, shape, place and orientation, measurable from the model. Most designers' models stop here.
- LOD 350: LOD 300 plus every interface with the elements around it: supports, connections, openings at their rough size, clearances. It is the level construction is coordinated at.
- LOD 400: detail enough to fabricate, assemble and install: reinforcement with its laps and hooks, bolts and welds, the parts a shop cuts. It is the level of shop drawings.
- LOD 500: not a higher level but a different kind: the element as found or as built, by observation, with its accuracy stated.
LOD is not LOI, and neither is the level of information need
Development (LOD) describes the geometry and the reliability of an element; information (LOI) describes the data it carries: its type, its material, its fire rating, its maker, its maintenance. A door can be drawn exactly (LOD 300) and still say nothing about its hardware (a low LOI). Ask for both, and ask for them separately.
ISO 19650 replaces the single number with the level of information need (EN 17412-1): for each purpose, each stage and each actor, what geometry (detail, dimensionality, location, appearance, parametric behaviour), what alphanumeric information and what documents an element must carry. A good execution plan writes the LOD table as a level of information need, so it can be checked rather than argued.
Calq keeps the two apart the same way: the geometry is the element's own (its type, its layers, its profile, its bars), the information is its properties and property sets, and the requirements are checked against an IDS file, the buildingSMART standard for information requirements.
Who models what, and when
Neither the AIA definitions nor BIMForum say who must model an element: a design team with the craft knowledge, or a contractor working inside the design model, may take an element to LOD 350 or 400. That is where one shared model pays: nobody redraws what the designer already modelled.
- Brief and concept (RIBA 0 to 2): LOD 100 and 200, by the design team: masses, zones, generic types
- Spatial coordination (RIBA 3): LOD 200 to 300: the main structure, the envelope and the main service routes at their size
- Technical design (RIBA 4): LOD 300 for everything the drawings define, LOD 350 where the team coordinates interfaces before tender
- Manufacturing and construction (RIBA 5): LOD 350 and 400, mostly by the trades: the steel detailer, the rebar detailer, the services contractor, the curtain wall maker
- Handover and use (RIBA 6 and 7): LOD 500 where the record is checked on site, with the information operation needs
How Calq serves every level
Calq is one BIM model in the browser for the whole team: architecture, structure, services and the site, linked or in one file, with Calq AI and the engines doing the repetitive modelling. An element is never redrawn to move up a level: the same wall, beam or duct gains its type, its layers, its interfaces and its fabrication parts in place, and every view, schedule and export reads the change at once.
- LOD 100 and 200: the setup, the brief, the plot study and the massing options, then generic walls, floors, roofs and zones laid by the engines
- LOD 300: typed elements with their build-ups, sizes and IFC classes; the structure on the grid; the services routed and sized; every drawing read from the model
- LOD 350: openings at their rough size made by the owner of the wall, supports and hangers, steel connections, clearances, and the coordination run across linked models
- LOD 400: reinforcement with its shapes and schedules, steel parts and workshop files, services cut into fabrication parts, pours and assemblies
- LOD 500: the as-built record element by element, point clouds as a reference, the asset register and COBie
Write the LOD table into the project
- Set the project up first: the Project menu, Start, Setup, or ask Calq AI "set up this project for a three storey office, with an LOD 300 model at technical design". The tool is propose_setup, then apply_setup; at the MCP door, use_tool with the same names.
- Write the information requirements as an IDS file and check the model against it with check_ids: the properties each element must carry at each stage are read, not remembered.
- Name the delivery under ISO 19650 (the Project menu, Present and issue, Delivery, or set_delivery): container names, statuses and revisions follow the one table, so an LOD 350 issue and an LOD 400 issue are told apart by their status and revision.
- Check before each issue: check_model for the model's own faults, coordination_report for the clashes across trades, and as_built_status once the site record begins.
- Read the level each element has reached against the BIMForum specification, trade by trade, with what it lacks for the next level: check_lod for the architecture, structure_lod for the structure, mep_lod for the services, read_landscape_lod and site_lod for the site.
The pages of this series
Each level has its own page: what it means element by element, how to build it in Calq step by step, how to check it and what to hand over. Then one page per trade at LOD 400, and the federated model and the deliverables that close a project.
Questions
What is the difference between LOD 300 and LOD 400?
LOD 300 is the element as designed, measurable at its true size and place. LOD 400 adds what is needed to make and install it: for concrete its reinforcement with laps and hooks, for steel its plates, bolts and welds, for services the parts a shop cuts and the hangers that hold them.
Does a model have one LOD?
No. LOD is given element by element, and one model holds many levels at once. An execution plan lists which element reaches which level at which stage.
Is LOD the same as level of detail?
No. Level of detail is how much an element is drawn; level of development is how far it can be relied on. A richly drawn element can still be a placeholder.
Which LOD should a design team deliver?
Most design teams deliver LOD 300 at technical design and LOD 350 where interfaces are coordinated before tender. LOD 400 is usually the trades' work, done inside the same model in Calq rather than redrawn.
Can Calq model at LOD 400?
Yes, for the elements shown on the trade pages of this series: reinforcement with shapes and bar schedules, steel connections with plates, bolts and welds and their workshop files, services cut into fabrication parts with their hangers, and the pours of the frame. Each page says what Calq lays and what stays the engineer's or the maker's decision.
How is LOD 500 different?
LOD 500 is the element as found on site, recorded by observation with its accuracy. In Calq the record is kept element by element with the day it was seen, by whom, and how far it stands from the drawing.